What is construction fund control?

Construction fund control is the practice of holding a project’s money with a neutral party that pays the contractor, subcontractors and suppliers only after each draw is verified. This guide explains how a controlled draw works, what bank examiners expect, which states regulate fund-control agents and how, how it compares with other ways to disburse, and the failures recent cases expose.

What fund control is

A neutral party between the money and the job.

Construction fund control is the practice of holding a project’s money with a neutral party that pays the contractor, subcontractors and suppliers only when the work, and the paperwork behind it, have been checked. It exists because construction money moves through long chains: lender to owner to general contractor to subcontractors to suppliers. Every link is a point where money can stop, be diverted or be paid on a false document.

Fund control is used by construction lenders who want independent verification of each draw, by owners and developers who want budget discipline, by sureties and owners who sometimes accept it in place of a performance bond [8], and increasingly by homeowners and their lenders on renovation and ADU projects.

How a fund-controlled draw works

Six steps, each with evidence.

StepWhat happensEvidence
1. SetupBudget, contracts and subcontracts are reviewed; disbursement categories are set; every payee is verifiedPlans and specs, signed contracts, lender’s statement of available funds [2]
2. FundingThe lender, owner or both fund the controlled account before work startsDeposit confirmation
3. Draw requestThe contractor requests payment for work completed in the periodPay application against the budget
4. VerificationAn inspector confirms progress; title is updated; prior-period lien releases are checkedInspection report, title date-down, lien waivers [1]
5. ReleasePayment goes to the contractor and, directly, to subcontractors and suppliers; the holdback is retainedPayment record per payee
6. CloseoutFinal lien releases and certificate of occupancy collected; holdback releasedFinal waivers, CO

These steps track what bank examiners expect of construction lenders: an inspection and title update with each draw, lien waivers from subcontractors and suppliers, a holdback, and all lien releases before the final draw. [1] See the examiner checklist mapped to release conditions.

Who may act as a fund-control agent

The law differs by state, and it matters who holds the money.

StateWhat the law says
NevadaThe Construction Control Law regulates anyone who controls or disburses construction funds. A construction control must deposit a surety bond with the State Contractors’ Board, from $20,000 up to $250,000 depending on its average trust balance (banks, title insurers and some lenders are exempt), and must follow statutory duties: obtain plans, contracts and subcontracts, compare them with available loan funds, disburse only within categories, and obtain lien releases before paying bills. Some contractors are required to use one. [2]
CaliforniaJoint control agents, who receive money to pay for labor and materials on construction, are licensed and regulated by the DFPI under the Escrow Law. [3] A joint control agent may not disburse for work until the work substantially complies with the control agreement, unless the principals instruct otherwise in writing. [4] Contractors using Registrar-approved joint control are exempt from home-improvement deposit and progress-payment limits. [5]
TexasConstruction payments and loan receipts are trust funds, and the contractor is the trustee; residential homestead jobs over $5,000 need a construction account. [6]
New YorkFunds received for improvements are held in trust under the Lien Law, and home-improvement payments before completion must be escrowed or bonded. [7]
Utah and other statesNo dedicated fund-control statute; the activity is generally governed by the state’s escrow, trust or money-transmission rules. Ask any fund-control provider who holds the money and under what license (how PayKeeper answers).

Fund control compared with other ways to disburse

Who holds the money, who checks, who pays.

ModelWho holds the moneyWho checks the workWho pays subs and suppliersMain weakness
Lender disburses to the contractorLenderLender’s inspectorContractorPass-through: money can stop at the contractor
Title company disbursingTitle companyOften the lenderTitle company or contractorUsually focused on lien coverage, not budget control
Fund controlNeutral fund-control agentAgent and inspectorAgent, directlyPaper-heavy if run by hand
Escrow with conditional releaseEscrow holderAgreed evidence: inspection, documents, dataEscrow holder, directly, in the same releaseConditions must be agreed up front

Where fund control fails, and how to avoid it

Lessons from 2025-2026 cases.

Accepting documents as proof. Two 2026 federal cases turned on forged lien waivers: one ended in an eight-year sentence, the other is a pending charge over nine fake waivers. A waiver collected from the contractor proves less than a payment made directly to the subcontractor.

Changing where money goes. A scammer who joined a live email thread on a California highway project redirected a $500,000 payment. Verify payees once and release only to those details.

Being slow. Developers report a 10-day median draw cycle, lenders 6.5 days (Rabbet, 2026), and new prompt-pay laws put clocks on payment. Agreeing the evidence in advance and releasing the day it arrives keeps fund control from becoming a bottleneck.

Sources

Statutes and official pages first; check the current text before relying on it.

  1. Comptroller’s Handbook: Commercial Real Estate Lending, Office of the Comptroller of the Currency.
  2. NRS chapter 627, Construction Control Law, Nevada Legislature.
  3. About the Escrow Law (escrow agents, joint control agents), California Department of Financial Protection and Innovation.
  4. Financial Code §17422 (joint control disbursement), via Justia.
  5. Business and Professions Code §7159.5, via Justia.
  6. Property Code Chapter 162, Texas Legislature.
  7. Lien Law §71-a, New York State Senate.
  8. Funds control: is this the key to bigger jobs? (Contractor Success Forum), Carpenter Company CPAs and McDaniel Whitley, podcast.

Questions

What is construction fund control?

A neutral party holds the project’s money and pays the contractor, subcontractors and suppliers only after each draw is verified with inspections, title updates and lien releases. It protects lenders and owners from paying for work that wasn’t done or bills that weren’t passed on.

Who uses fund control?

Construction lenders, developers and owners, sureties (some owners accept fund control in place of a bond), and increasingly homeowners and their lenders on renovation and ADU projects.

Does a fund-control company need a license?

Depends on the state. Nevada regulates construction controls under its Construction Control Law and requires a surety bond of $20,000 to $250,000; California licenses joint control agents under its Escrow Law. In other states, escrow, trust or money-transmission rules may apply. Always ask who holds the money and under what license.

How is fund control different from a lender disbursing draws?

When a lender disburses to the contractor, the contractor decides whether subcontractors and suppliers get paid. Under fund control, the neutral agent pays them directly after verifying the work, which reduces liens and diversion.

Is escrow the same as fund control?

Escrow with conditional release does the same job with a different mechanism: the money sits in escrow, the agreed evidence is verified, and one release pays every party owed. It extends fund control beyond construction loans to deposits, grants, insurance proceeds and platform payments. See PayKeeper fund control.