The changes
| State | Law | What changed | Effective |
|---|---|---|---|
| California | Civ. Code §§8811, 8818, 8820 | Private-project retainage capped at 5%; cannot be waived; withholding more carries a 2% a month penalty plus attorneys’ fees; flow-down to subs may not exceed the owner-GC rate [1] | January 1, 2026 |
| New York | SB 5655 | Clauses requiring more than 5% retainage on private contracts of $150,000 or more are void, closing a loophole in the 2023 cap [2] | Signed December 19, 2025 |
| Colorado | HB26-1311 | A contractor or sub may offer a retainage bond of up to 5% from a Colorado-licensed surety; if compliant, the owner must accept it and release retainage; private projects only [3] | Contracts from August 12, 2026 |
| Louisiana | Act 822 of 2026 | Downstream payment within 7 days (was 14); 1.5% a month penalty with no cap; on loan-funded projects payment is due by the later of 35 days or 5 days after the owner receives loan proceeds [4] | August 1, 2026 |
What the trend means
Every change shortens how long, or limits how much, an owner or general contractor can hold back. Retainage is moving from being working capital for whoever holds it toward being security with a clear end date. Louisiana goes furthest by tying the payment clock to the moment loan money arrives.
The details that matter, state by state
California. The 5% cap on private projects took effect January 1, 2026 and cannot be waived. Withholding more carries a 2% a month penalty plus attorneys’ fees, and retainage withheld from subcontractors may not exceed the owner-contractor percentage. There are exceptions, including subcontractors who fail to provide a required bond. [1]
New York. The state capped private retainage at 5% in 2023, but contracts could still require more. SB 5655, signed December 19, 2025, voids any clause in a private construction contract of $150,000 or more that requires retainage above 5%. [2]
Colorado. HB26-1311, signed May 7, 2026, lets a contractor or subcontractor offer a retainage bond from a Colorado-licensed surety for up to 5% of money earned; if the bond complies, retainage must be released at each tier. It applies to contracts entered on or after August 12, 2026, on private projects only. [3]
Louisiana. Act 822, effective August 1, 2026, requires owners to pay within 35 days of a written request, makes downstream payment due within 7 days instead of 14, and sets a 1.5% a month penalty with no cap and mandatory attorneys’ fees. On loan-funded projects, payment is due by the later of 35 days or 5 days after the owner receives loan proceeds. Public prompt pay is unchanged. [4]
Why legislators keep acting
The surveys explain the pressure. In Siteline’s 2026 survey of 492 mostly commercial respondents, 92% of subcontractors had floated payroll while waiting for payment and 28% did so most months; 43% of subcontractors waited 90 days or more for final payment and retainage, against 15% of general contractors. [5] Billd’s 2026 report found subcontractors wait an average of 51 days after a pay application while general contractors estimate 35, and 64% of subcontractors are slow-paid. [6] Rabbet found developers report a median 10 days from draw submission to funding, lenders 6.5. [7]
The wider credit picture points the same way: the National Association of Credit Management’s “dollar amount beyond terms” index rose to 51.9 in August 2026 from 48.8 in July. [8] When money upstream slows down, retainage is the first place it gets stuck.
What a 5% cap means in dollars
As an example, take a $2 million subcontract. At 10% retainage, $200,000 is held until the end of the job; at 5%, $100,000. If final payment and retainage take 90 days or more after completion, as they do for 43% of subcontractors in Siteline’s survey, [5] the cap frees $100,000 of the subcontractor’s own earned money for that whole period. For a firm already floating payroll, that is the difference between a credit line and none.
Cash, bond or escrow: three ways to hold retainage
| Method | Who holds the money | What the payee risks |
|---|---|---|
| Cash retainage (the default) | The owner or contractor, mixed with its own funds | Late release, and the holder’s insolvency |
| Retainage bond (Colorado HB26-1311) | The payee is paid; a surety guarantees the obligation | Bond premium and underwriting |
| Retainage in escrow | A neutral escrow holder, separate from both parties | Release still depends on the agreed conditions, which are written down in advance |
When a law ties payment to the arrival of loan proceeds, as Louisiana’s now does, [4] money already sitting in escrow makes the deadline easy to meet.
Retainage and the prompt-pay clock
Prompt-pay laws only help if the money exists when the clock runs out. Louisiana’s rule that payment is due five days after the owner receives loan proceeds [4] assumes the owner passes them on; California’s 2% a month penalty [1] assumes the payer notices the deadline. Both work better when the retained money is already set aside with a neutral holder and released by a recorded event, such as an inspection sign-off or a lien release, rather than by a person remembering to cut a check. That is the practical difference between retainage as security and retainage as working capital.
How escrowed retainage works, step by step
- The contract names the retainage rate, the escrow holder and the release conditions, such as substantial completion, punch-list sign-off, lien releases and a date.
- Each time a progress payment is approved, the retained share moves into the project’s escrow account instead of staying with the owner or contractor.
- Every tier can see the balance held for it.
- When the conditions are met, the escrow holder releases each party’s share directly, the general contractor’s and each subcontractor’s, in one release.
- The record of what was verified and when stays with the project, ready for a dispute, an auditor or a prompt-pay claim.
Questions a subcontractor should ask before signing
- What retainage rate applies, and is it within the cap where the project is?
- Is my retainage released when my scope is finished, or only when the whole project is?
- Who holds the retained money, and is it separate from the owner’s or contractor’s operating funds?
- Will a retainage bond or escrow be accepted in place of cash retainage?
- Which event starts the prompt-pay clock, and what is the penalty if it is missed?
A checklist for owners and general contractors
- Check every 2026 contract form against the cap that applies where the project is, including the flow-down to subcontractors.
- Set the retainage release conditions in the contract: completion evidence, lien releases, and a date.
- Track the prompt-pay clock from the event the statute names, such as a written request or receipt of loan proceeds.
- Decide in advance whether you will accept a retainage bond or escrow, and on what terms.
- Keep a record of each release and what supported it, for every tier.
Holding retainage in escrow
When retainage is held by a neutral escrow holder with a release date and conditions, nobody uses it as working capital and every tier can see when it moves. Prompt-pay deadlines become easier to meet because the money is already set aside and the release is triggered by the condition, not by someone remembering.
This tracker summarizes law-firm analyses; check the statute and your contract for any project.
Related on paykeeper.com: Construction fund control, Commercial real estate, Glossary: retainage, What is construction fund control?
Sources
- California expands 5 percent retainage cap to private projects, Holland & Knight, April 2026.
- New York closes retainage loophole: SB 5655, Holland & Knight, February 2026.
- HB 26-1311 signed into law: retainage bond alternative, Woods & Aitken, 2026.
- Louisiana overhauls prompt payment requirements for private construction projects, Cozen O’Connor, October 28, 2026.
- Subcontractors are still financing their own jobs, 2026 survey finds (Siteline), Contractor Magazine, September 4, 2026.
- Billd’s sixth annual National Subcontractor Market Report, Billd, June 23, 2026.
- 2026 State of Construction Finance report, Rabbet (vendor survey), August 14, 2026.
- Credit Managers’ Index, August 2026, National Association of Credit Management.
Lawsuits and criminal charges described here are allegations until decided. This post is general information, not legal advice.