Blog / Article

Retainage and prompt-pay laws 2025-2026: tracker

· PayKeeper, Inc.

Four states changed the rules on held-back construction money in a year. This tracker summarizes each change and links to the analysis it comes from. Last updated November 24, 2026.

The changes

StateLawWhat changedEffective
CaliforniaCiv. Code §§8811, 8818, 8820Private-project retainage capped at 5%; cannot be waived; withholding more carries a 2% a month penalty plus attorneys’ fees; flow-down to subs may not exceed the owner-GC rate [1]January 1, 2026
New YorkSB 5655Clauses requiring more than 5% retainage on private contracts of $150,000 or more are void, closing a loophole in the 2023 cap [2]Signed December 19, 2025
ColoradoHB26-1311A contractor or sub may offer a retainage bond of up to 5% from a Colorado-licensed surety; if compliant, the owner must accept it and release retainage; private projects only [3]Contracts from August 12, 2026
LouisianaAct 822 of 2026Downstream payment within 7 days (was 14); 1.5% a month penalty with no cap; on loan-funded projects payment is due by the later of 35 days or 5 days after the owner receives loan proceeds [4]August 1, 2026

What the trend means

Every change shortens how long, or limits how much, an owner or general contractor can hold back. Retainage is moving from being working capital for whoever holds it toward being security with a clear end date. Louisiana goes furthest by tying the payment clock to the moment loan money arrives.

Holding retainage in escrow

When retainage is held by a neutral escrow holder with a release date and conditions, nobody uses it as working capital and every tier can see when it moves. Prompt-pay deadlines become easier to meet because the money is already set aside and the release is triggered by the condition, not by someone remembering.

This tracker summarizes law-firm analyses; check the statute and your contract for any project.

What it means for each party

PartyWhat this means
SubcontractorsSmaller and shorter holdbacks; penalties when payment is late.
General contractorsMust flow payments down faster, often before being paid themselves.
OwnersLess security from held-back cash; bonds and escrow fill the gap.
LendersIn Louisiana, the payment clock now starts when loan money arrives.

Conditional release changes the position of every party at once: the money is committed, held by a neutral party, and paid directly to each party owed when the condition is verified. See who carries the risk, party by party.

Related on paykeeper.com: Construction fund control, Commercial real estate, Glossary: retainage

Sources

  1. California expands 5 percent retainage cap to private projects, Holland & Knight, April 2026.
  2. New York closes retainage loophole: SB 5655, Holland & Knight, February 2026.
  3. HB 26-1311 signed into law: retainage bond alternative, Woods & Aitken, 2026.
  4. Louisiana overhauls prompt payment requirements for private construction projects, Cozen O’Connor, October 28, 2026.

Lawsuits and criminal charges described here are allegations until decided. This post is general information, not legal advice.